REFERENCES - MAJOR PROJECTS COMPLETED RECENTLY:

  • Refurbishment of chemical treatment and smoke gases ducts TiO2, supply and erection of mixers and platforms and Neutralization process Plant in CINKARNA CELJE
  • Erection and welding of Alu bar busses Modification of cleaning plant HC 1 and in TALUM Kidričevo
  • Reconstruction of steam boilers and exchange of pipeline NaOH in JP ENERGETIKA Ljubljana
  • Erection steel structure of rack supported storage building KOVINOPLASTIKA Unec
  • Maintenance and overhaul of boiler and mills, overhaul of slug catcher in TPP TRBOVLJE
  • Supply and erection of pipelines, supply and erection of tanks and insulation Waste water treatment plant Laško
  • Turn-arounds in NUKLEAR POWER PLANT Krško
  • Maintenance of boiler mills, erection of measuring equipment, erection of pipelines and burners in TPP/TO Ljubljana
  • Supply and erection of equipment for fabrication Power and heating plant LJUBLJANSKE MLEKARNE, Ljubljana
  • Erection of technological equipment and mechanical and electrical works for process of thickening of whey in Ljubljanskih mlekarnah, obrat Maribor (dairy)
  • Dismantling and erection of equipment for project for Desulphuring Plant (I. and II. stage) v TPP Trbovlje
  • Erection of pipelines and supply and erection of supports for new tunnel varnish room (TTS) in Renault Revoz, Novo mesto
  • Design, supply and installation of electrical steam heaters in JP Energetika Ljubljana
  • Design, fabrication, supply, erection and corrosion protection of equipment for project Refurbishment of Calcium Plant I -II. stage (steel structure, elevator, furnace) in Silkem, Kidričevo
  • External pipeline of energetic media on pipe bridges in Ljubljanske mlekarne Ljubljana (dairy)
  • Exchange of superheater of header PP2 on boiler 4 in TPP Šoštanj
  • Exchange of end superheaters on boilers 1 and 2 and erection of stop valve NO 250, NP 320 bar v TPP/TO Ljubljana
  • Supply and erection of equipment for continuous product line for chipboards LESNA, Otiški Vrh (equipment supplied by Metso)
  • Supply and erection of mechanical equipment and piping for Waste Water Treatment Plant Saleška dolina
  • Steam pipeline for paper machine 2, supply and erection - pipeline Modernization of paper machine 3, supply and erection – mechanical works Displacement of warehouse H2O2 in VIPAP Videm Krško (paper and pulp plant)
  • Maintenance works - mechanical piping maintenance in Pivovarna Union (brewery)
  • Erection of biomass boiler and belonging mechanical equipment in Furnirnica Merkscha Celje (plywood plant)
  • Dismantling and erection works of production line for fibre plates and grinding line in LESONIT, Ilirska Bistrica
  • Dismantling and erection works of boiler Block 1 in TPP Kosovo B1
  • Supply, fabrication and erection of steel structure and erection of pressure part of boiler TPK Zagreb in incineration TOPLARNA CELJE
  • Reconstruction of rolling mill furnace in thick steel plates plant and supply and erection of support steel construction of ducts and pipelines for furnaces in ACRONI Jesenice
  • Partly supply and assembling of pipelines, hardware and material equipment for Waste Water Treatment Plant in MLEKARNI CELEIA Arja Vas (creamery)
  • Reconstruction and mechanical works of the reconstruction and completion of WWTP Prašičereje Podgrad (pig farm)
  • Erection of biomass boiler and erection of belonging mechanical equipment (ducts, pipelines, landings,…) PAVATEX, Švica
  • Erection of mechanical equipment for walking beam furnace capacity 280 t/h in Steel plant DUFERCO, La Louviere, Belgija
  • Erection of mechanical equipment for walking beam furnace capacity 280 t/h and supply of ducts, landings and steel structure in Steel plant DUNAFERR, Dunaujvaros Hungary
  • Erection of fermentor Waste Water Treatment Plant GRAZERFELD, Austria
  • Supply and erection - pipelines for mechanical technological pipelines of Terminal for reception of oil and warehouse for alcohol in LUKA KOPER (port)
  • Erection of biomass boiler and belonging equipment (steel structure, ducts and pipelines ) in Biomase Heitzkraftwerk, RWE - WITTGENSTEIN, Germany
  • Erection of biomass boiler and belonging equipment (steel structure, ducts and pipelines) in ENARBOIS SA, Rueyres, Switzerland;
  • Erection of biomass boiler and belonging equipment (steel structure, ducts and pipelines) in AEB ALPES ENERGIE BOIS, Le Cheylas, France
  • Repair of leakage at exchangers, the supply and installation of mechanical and electrical equipment for evaporate cooling, supply and erection of pipelines for the Unit “Plastenka”, various processing and dismantling works in “LJUBLJANSKE MLEKARNE”
  • Replacement of metal compensators, refrigerator repair at boiler 2, supply and erection of piping in order to cool the grades K3 in “TETO Ljubljana”
  • Replacing of the gearbox and of the running wheel in “LAFARGE CEMENT, Trbovlje”
  • Construction of the “facility 16.3” for the sugar receiver plant (civil works, steel construction delivery, steel construction erection, electrical and mechanical works)
  • Reconstruction of “CČN PTUJ” plant – installation of mechanical equipment and of piping
  • Erection of piping and partly of mechanical equipment at “ČN Razkižje« and »ČN Velika Polana«
  • Erection of 8 mills of the boiler and ash removal plant at Block F and G, KW Neurath, Germany (for the client ALSTOM, Germany)
  • Preparation of membrane walls in the range of boiler burners (12 units) for KW Westfalen Block E and D (for the client ALSTOM, Germany)
  • Pretakališče Petrol Plin  - Supply and installation of pipelines and installation of mechanical equipment related to new construction and relocation of DECANTING STATION AND INCREASE OF CAPACITY OF THE STORAGE UNP Store - Phase I  
  • Installation of panels, burners (24 burners), and OFA channels at the site EDF Cordemais, France (for the client BBS, Germany)
  • Installation of the boiler and equipment Naturenergie Cham, Germany
NEWS
15.11.2011
Actually project under construction
Following types of works are carried out at the moment: Production of heating surface for thermal power plant Šoštanj, block 6, assembly works in Cham, Germany, various welding and piping works in Koper, pipe conversion for secundary jet spray in Acroni Jesenice.Erection of 8 sets of mills for Bloc F and G TPP Neurath, Germany , fabrication of pipe coil wall for burners for TPP Westfal.E, Germany, turn-arounds in TPP Trbovlje, TPP&H Ljubljana,
 More informations >
PROFILE
Himomontaža,
Company for instalation, manufacturing and services Llc.

Sokolska ulica 60
2000 MARIBOR
ID for VAT: SI97594768

Tel: +386 (0)2 480 52 10
Fax: +386 (0)2 480 52 21
Email: info@himomontaza.si

Nova KBM:
BA: 04515-0000174914
SWIFT: KBMASI2X
IBAN: SI56045150000174914

Bank Austria Creditanstalt:
BA: 29000-0055259011
SWIFT: BACXSI22
IBAN: SI56290000055259011
  Copyright © 2009 Himomontaža d.o.o. - All rights reserved | web design: Conectivia